|
|
| A
New Well on the Mountaintop
Continued...
|
per day. That same year we drilled another well to 160
feet and it produced about 2,500 gallons a day for that first year, but
after sitting over the winter lost its luster and never produced more
that 1,000 gallons a day.
The fall of 2002 we put in our 125,000 gallon steel water tank that gave
us the ability to store water for the heavy use times until we had a good
producing well. The first winter gave us some challenges and we could
only bring in 700 gallons at a time. On new years we lost 40,000 gallons
through a leak and had to haul water through the night to keep our guest
in showers.
The spring of 2003 we drilled a well to 1,000 feet that came up dry. The
summer of 2003 we had regular trips from a water truck that pumped 5,000
gallons at a time. Then August we started yet another well, with the advice
of two witchers that said there is water at 400 to 500 feet. We went to
500 then 1,000 and still no water.
Sat down with the driller and decided that we would go 1,500 feet, even
though the cost starts going up exponentially. He finished in November
after going out and purchasing a third compressor (these aren’t
the type you have in your garage, they come mounted to a semi trailer.)
The well driller got down to 1,100 feet and had to set an 8 inch inside
diameter pipe in the hole so he could blow the tailings out of the hole
(otherwise the air had too many escape passages).
With the eight inch pipe in place he placed a 7 5/8 inch drill down the
hole and drilled to 1,520 feet. We found water in the range of 6 to 10
gallons a minute. The next step was to put a 6 inch inside diameter pipe
from 1100 feet down to 1520 feet, concrete in the first 100 feet from
the surface from the eight inch pipe to the outside of the twelve and
half inch hole. Now we were ready for our pump man and the electrician.

We set the pump at 1,400 feet as the water
level in the hole was static at 1,200 feet. We ran electrical lines and
yes the electrician was 3 months late getting his work done so the pump
installer used a caterpillar to get his rig up the 3 mile road. With snow
flying we were able to set the pump with 500 feet of one inch pipe and
900 feet of two inch pipe that was special made for oil fields.
The weight of the 3 strand ‘O’ cable with ground wire weighted
2,500 pounds by itself without the 7.5 HP pump and the pipe. Finally set
we needed the electrician to finish installing a special variable speed
drive that allows the pump to start slowly and then pickup speed. That
process finished about the middle of March and then off to the water lab
with samples to be tested. We found 2.6 parts per million of iron which
meant we needed to condition the water.
On Monday the 24th of April (yes we did start this project the first of
August) we started pumping water to our water tank. We filter the water
at the well head, chlorinate it and send it on to the water tank. Coming
into the building under the yoga floor we already had an ultraviolet light
sanitation system, added now is a 4 cubic foot carbon filter that will
take out the iron (oxidized by the chlorine) and the chlorine.
It has been a long and frustrating process, but done and we have a water
system that works. For those that bemoaned your water bill, know that
we currently have invested in wells and tank approximately $250,000. The
price one pays to be in the middle of paradise.
Now we have water that can be drunk straight from the tap and is probably
better that most bottled water. We haven’t tested it yet but the
water we are getting could be 50 to 100 years old. That means that this
six year drought we are in the middle of won’t be affecting our
water source.
 |
by
John Epert |
|